Our work at Medland House in Alfold included the setup of the site compound, temporary haul roads, and loading bays to support site operations, followed by piling and traditional footings to form the foundations for the build. We completed all drainage and service installations, along with scaffold mats to the building perimeters, plot clearance, and screen wall foundations, before delivering the roads and completing both hard and soft landscaping to finish the project.